WINDSOR- BRIDGE REPLACEMENT, W-41-020, HIGH STREET HILL ROAD OVER WESTFIELD BROOK (AKA- POLLY HARWOOD BRIDGE)
The proposed work includes the reconstruction of the bridge and the improvements necessary to provide a bridge structure capable of carrying statutory loading. Highway improvements consist of guardrail installations at the approach roadway to the bridge. Minor alterations in the High Street Hill Road are expected to improve the safety of the roadway including the sight distance. The pedestrian traffic will be maintained during construction. A detour will be provided during project construction.
Location:
  • Town of Windsor
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $735,787.00
    Construction Bid Price: $638,945.70
    Initial Construction Estimate: $710,243.75
    District: District 1

    Contracts (2) Progress
    # 61916 -- Construction Contract
    Bridge Replacement (W-41-020) (Concord) - High Street over Westfield Brook (Polly harwood Bridge). (ABP) Completed
    # 95261 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTJ Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/22/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/17/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 10/31/2009
    Project Status Advertised 12/26/2009
    Project Management
    100% Design 100% Package Received 06/06/2008
    25% Design 25% Package Received 03/05/2002
    25% Design 25% Package Comments to DE 06/26/2002
    25% Design Design Public Hearing 03/13/2002
    25% Design Design Public Hearing 04/07/2009
    75% Design 75% Package Received 07/08/2003
    75% Design 75% Package Comments to DE 05/26/2004
    Final Design PS&E Received 02/05/2009
    Final Design PS&E to FAPRO 10/26/2009
    Consultant Contract Process Scope to DE 09/30/1998
    Consultant Contract Process NTP Issued 12/09/1998
    Consultant Contract Process Workhours Approved 11/10/1998