Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHAMPTON- TRAFFIC SIGNALS, INTERSECTION OF NORTH MAPLE STREET AND BRIDGE ROAD. FA# STP-001S(286)X
This project will enhance safety and improve the efficiency of traffic flow at the intersection of North Maple Street and Bridge Road in Northampton by replacing the existing flashing red/yellow beacon with a fully actuated traffic signal. The new signals will include an exclusive push-button pedestrian phase and a pre-emption phase for emergency vehicles. Work also includes the realignment of approaches and a minor widening of Bridge Road in order to add exclusive left turn only lanes. Signs and pavement markings are also included.
Location:
  • City of Northampton
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $633,203.00
    Construction Bid Price: $534,593.80
    Initial Construction Estimate: $474,017.25
    District: District 2
    Current Status: Project physically complete (as of 03/08/2007)

    Contracts (1) Progress
    # 43570 -- Construction Contract
    Northampton - Roadway Reconstruction at the Intersection of Bridge Road at North Maple Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/17/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project physically complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/22/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 06/11/2005
    Project Management
    100% Design 100% Package Received 03/26/2004
    100% Design 100% Package Comments to DE 05/10/2004
    25% Design 25% Package Received 01/11/2000
    25% Design 25% Package Comments to DE 03/31/2000
    75% Design 75% Package Received 12/14/2000
    75% Design 75% Package Comments to DE 02/09/2001
    Final Design PS&E Received 05/18/2005
    Final Design PS&E to FAPRO 06/06/2005