Project Description:
WILBRAHAM- BRIDGE REHABILITATION, W-35-003, RED BRIDGE ROAD OVER NE UTILITIES CANAL
This project consists of demolishing and replacing the Red Bridge Road Bridge over the Utilities Canal in Wilbraham. The new bridge will be a superstructure replacement constructed on an improved alignment. The substructure of the bridge will be integrated with the granite block canal walls. Also included in the work is clearing and grubbing, excavation, reconstruction of approach roadways, furnishing and installing guard rail, granite transition curb, and any incidental work.
Location:
  • Town of Wilbraham
  • Resident Engineer: Michael Mack
    Construction Contract Value: $1,658,446.00
    Construction Bid Price: $1,492,224.30
    Initial Construction Estimate: $2,047,825.00
    District: District 2

    Contracts (2) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 59053 -- Construction Contract
    Bridge Superstructure Replacement (W-35-003) (Steel) - Red Bridge Road over the Utilities Canal. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/23/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/06/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Review Committee Letter 10/05/1998
    Project Status Advertised 06/06/2009
    Project Management
    100% Design 100% Package Received 03/06/2001
    100% Design 100% Package Comments to DE 10/10/2001
    25% Design 25% Package Received 08/26/1999
    25% Design 25% Package Comments to DE 10/08/1999
    25% Design Design Public Hearing 12/08/1999
    75% Design 75% Package Received 06/08/2000
    75% Design 75% Package Comments to DE 08/17/2000
    Final Design PS&E Received 12/07/2006
    Final Design PS&E Received 04/01/2009
    Final Design PS&E to FAPRO 05/12/2009
    Final Design PS&E to FAPRO 06/03/2009