Project Description:
AGAWAM- RECONSTRUCTION OF ROUTE 159 (MAIN STREET) FROM CONNECTICUT S.L. TO ROUTE 75, INCLUDES REHAB OF A-05-009
The Agawam Traffic and Safety Improvement Project is located along the Main Street (Route 159) corridor and consists of seven improvement locations. At Location 1 and 2 the roadway will be widened minimally, then repaved. At Location 2 the traffic signal at the intersection of River Road and Main Street will be reconstructed with all new mast arms, foundations, loops, cable, and signal posts. The major improvements to Main Street at Locations 3, 4, 5, and 6 include improving the existing traffic signals, widening, resurfacing, and re-striping Main Street, and building an Emergency Vehicle Traffic Signal at the Agawam Fire Station. At Location 7, fully-actuated signals are proposed.
Location:
  • City of Agawam
  • Resident Engineer: Hannah Lapointe
    Construction Contract Value: $4,189,074.00
    Construction Bid Price: $3,716,849.14
    Initial Construction Estimate: $3,155,990.00
    District: District 2

    Contracts (4) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64318 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75490 -- Construction Contract
    Roadway Reconstruction and Related Work along Sections of Route 159 (Main Street). Completed
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/26/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/06/1998
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/26/2002
    Project Status Advertised 08/18/2012
    Project Management
    100% Design 100% Package Received 03/25/2010
    100% Design 100% Package Received 12/23/2010
    100% Design 100% Package Comments to DE 11/05/2010
    100% Design 100% Package Comments to DE 03/09/2011
    100% Design 100% Plans Complete 07/06/2010
    25% Design 25% Package Received 07/18/2003
    25% Design 25% Package Received 06/27/2008
    25% Design 25% Package Comments to DE 10/22/2003
    25% Design Design Public Hearing 04/22/2009
    75% Design 75% Package Received 07/09/2009
    75% Design 75% Package Comments to DE 08/17/2009
    Final Design PS&E Received 02/10/2012
    Final Design PS&E Received 02/10/2012
    Final Design PS&E Received 02/10/2012
    Final Design PS&E Received 07/13/2012
    Final Design PS&E to FAPRO 08/15/2012