CHARLTON- OXFORD- RECONSTRUCTION ON ROUTE 20, FROM RICHARDSON'S CORNER EASTERLY TO ROUTE 12, INCLUDES REHAB OF C-06-023 & REPLACEMENT OF O-06-002
The project begins on Route 20 at Richardson's Corner in Charlton and continues easterly 3.2 miles to the Route 12 intersection in Oxford. The project entails highway reconstruction, widening, traffic signals and installation of median barrier. The bridges carrying US 20 over the Little River in Charlton and US 20 over the French River in Oxford will also be rehabilitated.
Location:
  • Town of Charlton
  • Town of Oxford
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2022
    Project Manager: Susan Harrington
    Estimated Total Contract Cost: $71,541,392.77
    Estimated Total Federal Participating Construction Cost: $78,222,751.88
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 04/23/2022 )

    Contracts (7) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 52398 -- Design -- Highway
    Work will consist of Final Design Services to complete the project from 25% Design Stage to PS&E/Advertising Stage for Highway Reconstruction in Charlton/Oxford. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 68387 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80660 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
  • Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. CMAQ reduced from $1,018,243 to $123,655.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $98,924.00
    State Cost: $24,731.00
    Total Cost: $123,655.00

    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
  • Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. 2024 HSIP removed.
  • No funding records for this TIP line

    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
  • Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. STBG funding removed.
  • No funding records for this TIP line

    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
  • Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. NHPP decreased from $10,895,727 to $7,956,218.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $6,364,974.40
    State Cost: $1,591,243.60
    Total Cost: $7,956,218.00

    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,220,840.00
    State Cost: $555,210.00
    Total Cost: $2,776,050.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/12/1998
    Project Review Committee PRC Approved 09/30/1998
    Project Review Committee Letter 09/30/1998
    Project Status Advertised 04/23/2022
    Project Management
    100% Design 100% Package Received 03/31/2022
    25% Design 25% Package Received 02/05/2018
    25% Design 25% Package Received - Resub 1 06/26/2020
    25% Design 25% Package Received - Resub 2 12/14/2021
    25% Design Design Public Hearing 02/22/2016
    25% Design Design Public Hearing 05/13/2021
    Consultant Contract Process NTP Issued 07/16/2010