Project Description: |
CHARLTON- OXFORD- RECONSTRUCTION ON ROUTE 20, FROM RICHARDSON'S CORNER EASTERLY TO ROUTE 12, INCLUDES REHAB OF C-06-023 & REPLACEMENT OF O-06-002
The project begins on Route 20 at Richardson's Corner in Charlton and continues easterly 3.2 miles to the Route 12 intersection in Oxford. The project entails highway reconstruction, widening, traffic signals and installation of median barrier. The bridges carrying US 20 over the Little River in Charlton and US 20 over the French River in Oxford will also be rehabilitated.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2022 |
Project Manager: | Christopher P Gagne |
Estimated Total Contract Cost: | $71,541,392.77 |
Estimated Total Federal Participating Construction Cost: | $78,222,751.88 |
Funding Provision: | This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | This project has been advertised for construction bids. (as of 04/23/2022 ) |
|