Planned Federal FY: |
2024 |
Responsible MPO: |
Central Massachusetts Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHARLTON OXFORD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2B |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
|
|
Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. CMAQ reduced from $1,018,243 to $123,655.
|
|
Category |
FA - Congestion Mitigation/Air Quality (CMAQ) |
|
Federal Cost: |
$98,924.00 |
State Cost: |
$24,731.00 |
Total Cost: |
$123,655.00 |
|
|
|
Planned Federal FY: |
2024 |
Responsible MPO: |
Central Massachusetts Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHARLTON OXFORD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2B |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
|
|
Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. 2024 HSIP removed.
|
|
No funding records for this TIP line
|
|
Planned Federal FY: |
2024 |
Responsible MPO: |
Central Massachusetts Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHARLTON OXFORD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2B |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
|
|
Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. STBG funding removed.
|
|
No funding records for this TIP line
|
|
Planned Federal FY: |
2024 |
Responsible MPO: |
Central Massachusetts Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHARLTON OXFORD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2B |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
|
|
Funding allocations adjusted to match actual obligations and meet fiscal constraint via STIP Action 3. NHPP decreased from $10,895,727 to $7,956,218.
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS |
|
Federal Cost: |
$6,364,974.40 |
State Cost: |
$1,591,243.60 |
Total Cost: |
$7,956,218.00 |
|
|
|
Planned Federal FY: |
2025 |
Responsible MPO: |
Central Massachusetts Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHARLTON OXFORD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction, Total Project Cost = $78,222,752, CMAQ + NHPP + STBG Project is AC'd between 2022 and 2025, PM Score = 22 out of 27, Advertised on 4/23/22
|
|
Category |
FA - Congestion Mitigation/Air Quality (CMAQ) |
|
Federal Cost: |
$2,220,840.00 |
State Cost: |
$555,210.00 |
Total Cost: |
$2,776,050.00 |
|
|
|
|