Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLYOKE- TRAFFIC SIGNALS (WESTFIELD RD.) AT HOMESTEAD AVE. & CHERRY ST. AT HILLSIDE AVE AT ROUTE 202
The purpose of this to project is to upgrade the intersections through the provision of a new traffic control signal system, signs and pavement markings.
Location:
  • City of Holyoke
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Brian Chapman
    Estimated Total Contract Cost: $1,410,636.77
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 06/25/2005 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/20/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 06/25/2005
    Project Management
    100% Design 100% Package Received 09/06/2002
    100% Design 100% Package Comments to DE 11/06/2002
    25% Design 25% Package Received 11/01/2000
    25% Design 25% Package Comments to DE 12/13/2000
    75% Design 75% Package Received 04/17/2002
    75% Design 75% Package Comments to DE 06/06/2002
    Final Design PS&E Received 05/18/2005
    Final Design PS&E to FAPRO 06/07/2005