Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLYOKE- TRAFFIC SIGNALS (WESTFIELD RD.) AT HOMESTEAD AVE. & CHERRY ST. AT HILLSIDE AVE AT ROUTE 202
The purpose of this to project is to upgrade the intersections through the provision of a new traffic control signal system, signs and pavement markings.
Location:
  • City of Holyoke
  • Resident Engineer: Joseph Hogan
    Construction Contract Value: $1,410,636.77
    Construction Bid Price: $1,015,854.25
    Initial Construction Estimate: $900,791.00
    District: District 2
    Current Status: Physical work complete (as of 01/29/2007)

    Contracts (1) Progress
    # 43146 -- Construction Contract
    Holyoke - Intersection Reconstruction at 2 Locations Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/21/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/20/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 06/25/2005
    Project Management
    100% Design 100% Package Received 09/06/2002
    100% Design 100% Package Comments to DE 11/06/2002
    25% Design 25% Package Received 11/01/2000
    25% Design 25% Package Comments to DE 12/13/2000
    75% Design 75% Package Received 04/17/2002
    75% Design 75% Package Comments to DE 06/06/2002
    Final Design PS&E Received 05/18/2005
    Final Design PS&E to FAPRO 06/07/2005