Project Description: |
HINSDALE- BRIDGE REPLACEMENT, BR# H-16-002 MAIN STREET OVER THE EAST BRANCH OF THE HOUSATONIC RIVER
The existing bridge will be replaced by a single span steel truss bridge with a reinforced concrete deck slab. The approach roadway will also be improved.
|
Location: |
|
Resident Engineer: | Mark De Vylder |
Construction Contract Value: | $1,357,480.00 |
Construction Bid Price: | $1,206,800.00 |
Initial Construction Estimate: | $1,321,170.00 |
District: | District 1 |
|