GREENFIELD- BRIDGE CONSTRUCTION, FRANKLIN COUNTY BIKEWAY OVER THE GREEN RIVER
Location:
  • Town of Greenfield
  • Resident Engineer: Theodore Miga
    Construction Contract Value: $272,750.00
    Construction Bid Price: $237,598.25
    Initial Construction Estimate: $171,000.00
    District: District 2

    Contracts (1) Progress
    # 31193 -- Construction Contract
    FRANKLIN COUNTY BIKEWAY / GREEN RIVER Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/30/2001
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 05/24/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/30/2000