| Project Description: |
GEORGETOWN- NEW ACCESS ROAD FROM ROUTE 133 TO TENNEY STREET INCLUDING NEW BR# G-03-002 ACCESS ROAD OVER MUDDY BROOK
This project will result in the construction of a new 3,609 feet long access road between National Ave in the south and Norino Way in the north. Additional work includes: roadway drainage system, water line installation, guardrail, wetlands replication, and other associated work.
|
| Location: |
|
| Resident Engineer: | Charles Amato![]() |
| Construction Contract Value: | $3,812,979.00 |
| Construction Bid Price: | $2,996,518.00 |
| Initial Construction Estimate: | $2,642,374.60 |
| District: | District 4 |
| Current Status: | The following work is left to be completed by the contractor , Loaming and seeding, erosion control blanket and general cleanup. (as of 03/29/2007) |
| Additional Info: | Final inspection was conducted in December of 2006. A punch list was written up and given to the contractor for completion by April 11, 2007. (as of 03/29/2007) |
|