WALPOLE- TRAFFIC SIGNALS, ROUTE 1A (MAIN STREET) AND WINTER STREET
The purpose of this project is to provide geometric improvements and a new traffic signal at the intersection of Route 1A (Main Street) with Winter Street and Jean Road.
Location:
  • Town of Walpole
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $1,210,815.16
    Construction Bid Price: $944,208.00
    Initial Construction Estimate: $850,960.00
    District: District 5

    Contracts (2) Progress
    # 44809 -- Construction Contract
    Walpole - Intersection Improvements Including Signals at Route 1A (Main Street) at Winter Street and Jean Road Completed
    # 98474 -- Design -- Highway
    Walpole - Route 1A (Main Street) at Winter St and Jean Road Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/15/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/23/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 09/24/2005
    Project Status Advertised 02/04/2006
    Project Management
    100% Design 100% Package Received 04/01/2005
    100% Design 100% Package Comments to DE 05/24/2005
    25% Design 25% Package Received 05/05/2000
    25% Design 25% Package Comments to DE 08/22/2000
    25% Design Design Public Hearing 09/10/2002
    75% Design 75% Package Received 08/14/2003
    75% Design 75% Package Comments to DE 11/26/2003
    Final Design PS&E Received 08/15/2005
    Final Design PS&E to FAPRO 08/22/2005