Project Description:
WAYLAND- BRIDGE REPLACEMENT, W-11-002, PELHAM ISLAND ROAD OVER THE SUDBURY RIVER
The proposed project will replace the existing bridge with a replicated arch structure, similar to the existing bridge. The bridge rail will be a concrete Texas style rail, also similar to the existing rail type. Minor roadway improvements will eliminate drainage problems. A traffic detour is necessary for the duration of the project. Currently, the bridge remains open with the aid of a temporary acrow panel structure which will remain in place until the construction begins.
Location:
  • Town of Wayland
  • Resident Engineer: Alan Webb
    Construction Contract Value: $2,574,844.00
    Construction Bid Price: $2,327,804.00
    Initial Construction Estimate: $1,925,000.00
    District: District 3

    Contracts (5) Progress
    # 37076 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge rehabilitation/Replacement/Preservation Program. Final
    # 59591 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70377 -- Construction Contract
    Bridge Replacement (W-11-002) (Concrete) - Pelham Island Road over the Sudbury River. Completed
    # 95262 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTK Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/18/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/30/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Approved 25% 10/04/2002
    Project Status Advertised 09/30/2005
    Project Status Advertised 08/06/2011
    Project Management
    100% Design 100% Package Received 02/17/2005
    100% Design 100% Package Comments to DE 04/20/2005
    25% Design 25% Package Received 06/12/2001
    25% Design Design Public Hearing 05/15/2002
    75% Design 75% Package Received 10/23/2002
    75% Design 75% Package Comments to DE 04/15/2003
    Final Design PS&E Received 07/22/2005
    Final Design PS&E Received 10/14/2010
    Final Design PS&E Received 11/26/2010
    Final Design PS&E to FAPRO 07/29/2005
    Final Design PS&E to FAPRO 08/21/2006
    Final Design PS&E to FAPRO 08/02/2011