| Project Description: |
CHELSEA- REVERE- HIGHWAY LIGHTING REPLACEMENT PROJECT, ROUTE 1 (NORTHEAST EXPRESSWAY)
|
| Location: |
|
| Resident Engineer: | Ronald Baratta![]() |
| Construction Contract Value: | $460,545.00 |
| Construction Bid Price: | $412,405.00 |
| Initial Construction Estimate: | $379,721.35 |
| District: | District 4 |
| Current Status: | This project held a final inspection on 5/22/2007 and was accepted. It is now complete (as of 05/30/2007) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||