Project Description:
WEBSTER- RESURFACING AND RELATED WORK ON SCHOOL STREET FROM PERRYVILLE RD./ASH ST. NORTHERLY TO ROUTE 12 (MAIN ST)
The purpose of this project is to resurface School Street to provide a 9-meter paved street width with widening where necessary. The street width will be comprised of two-3.25 meter travel lands and two 1.25-meter shoulders. The project is 2500 meters in length. Sidewalk and curb construction/reconstruction are also proposed. A sidewalk is proposed on the west side of School Street from Ash Street to Highland Street. From Highland Street to Main Street (Route 12), sidewalks are proposed on both sides of the street.The work includes cold planing existing pavement, hot mix asphalt overlay, box widening, full depth reconstruction, drainage system improvements, granite curb installation, hot mix asphalt sidewalk construction/reconstruction, concrete handicapped ramp construction, hot mix asphalt driveway construction, pavement marking and sign installation, landscaping, other incidental items necessary.
Location:
  • Town of Webster
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $1,538,080.91
    Construction Bid Price: $1,112,097.00
    Initial Construction Estimate: $1,125,974.00
    District: District 3
    Current Status: Completed the installation of EWO # 1 Stone Masonry Walls. (as of 07/10/2006)
    Additional Info: Mass Electric to begin removal of utilities poles the week of July 10, 2006 (as of 07/10/2006)

    Contracts (1) Progress
    # 36914 -- Construction Contract
    Webster - Resurfacing and Related Work on a Section of School Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/04/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Completed the installation of EWO # 1 Stone Masonry Walls.
    Additional Info
    Mass Electric to begin removal of utilities poles the week of July 10, 2006
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/13/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 09/11/2004
    Project Management
    100% Design 100% Package Received 05/18/2004
    100% Design 100% Package Comments to DE 06/18/2004
    25% Design Design Public Hearing 07/11/2000
    75% Design 75% Plans Complete 12/11/2004
    Final Design PS&E Received 08/05/2004
    Final Design PS&E to FAPRO 08/05/2004