SHREWSBURY- RESURFACING & RELATED WORK ON MAIN STREET, FROM I-290 RAMPS EASTERLY TO MAPLE AVENUE
This project begins at the I-290 Ramps continuing easterly to Maple Avenue and consists of resurfacing with minor box widening and sidewalk construction. (1.75 mi) 2 Lanes
Location:
  • Town of Shrewsbury
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Shawn Holland
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • S14024 
    See the Milestone Details tab for additional Project information