Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CANTON- IMPROVEMENTS & SIGNALIZATION, ROUTE 138 (TURNPIKE STREET) AT WASHINGTON STREET AND ROUTE 138 AT RANDOLPH STREET
The roadway improvements proposed in this project are associated in part with the construction of Reebok world Headquarters. As part of the approval process for this development, traffic signal and geometric improvements to the roadway are required at the intersection of Route 138 at Washington and Randolph Streets. Also included in this project are roadway widening, new sidewalks, bicycle accommodations, traffic signal modifications, improved pavement markings and signing, drainage system modifications and retaining wall construction.
Location:
  • Town of Canton
  • Resident Engineer: Phuong Tran
    Construction Contract Value: $2,990,581.75
    Construction Bid Price: $2,195,064.50
    Initial Construction Estimate: $1,623,182.75
    District: District 4

    Contracts (1) Progress
    # 43286 -- Construction Contract
    Canton - Roadway Reconstruction at the Intersections of Route 138 (Turnpike Street) at Washington Street and Route 138 (Turnpike Street) at Randolph Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/12/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/14/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Status Advertised 06/11/2005
    Project Management
    100% Design 100% Package Received 02/14/2005
    100% Design 100% Package Comments to DE 05/17/2005
    25% Design 25% Package Received 01/01/2002
    25% Design 25% Package Comments to DE 10/08/2003
    25% Design 25% Package Approved 10/07/2003
    25% Design Design Public Hearing 11/24/2003
    75% Design 75% Package Received 08/31/2004
    75% Design 75% Package Comments to DE 12/31/2004
    Final Design PS&E Received 06/07/2005
    Final Design PS&E to FAPRO 06/07/2005