ATTLEBORO- RECONSTRUCTION OF ROUTE 152 (NORTH MAIN & SOUTH MAIN STS) FROM HOLCOTT DRIVE TO THE NORTH ATTLEBORO T.L. (PHASE I)
The limits of this project extend from Holcott Drive northerly to the North Attleborough town line on North Main Street, and from the North Main Street/Toner Boulevard intersection westerly to the North Attleborough town line. Proposed improvements will include the construction of an exclusive left hand turn lane from the I-95 Northbound off-ramp to Toner Boulevard eastbound. North Main Street will be improved by removing the free right turn lane from North Main Street southbound to Toner Boulevard westbound. North Main Street northbound will be widened to accommodate 2 left turn lanes on to Toner Boulevard westbound. Traffic signals will be constructed at the Toner Boulevard and I-95 Northbound ramps intersection. Existing traffic signals located at the North Main Street and Toner Boulevard intersections will be replaced.
Location:
  • City of Attleboro
  • Resident Engineer: Michael Giovanelli
    Construction Contract Value: $2,968,567.00
    Construction Bid Price: $2,492,484.15
    Initial Construction Estimate: $2,939,745.00
    District: District 5

    Contracts (1) Progress
    # 54654 -- Construction Contract
    Attleboro - Roadway Reconstruction & Related Work on a Section of Tower Blvd at I-95 Ramps Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/16/1998
    Project Status Advertised 09/15/2007
    Project Management
    100% Design 100% Package Received 06/20/2007
    100% Design 100% Plans Approved 09/19/2007
    25% Design 25% Package Received 06/23/2003
    25% Design 25% Package Comments to DE 09/19/2003
    25% Design Design Public Hearing 08/30/2005
    75% Design 75% Package Received 12/28/2005
    75% Design 75% Package Comments to DE 11/24/2006