Project Description: |
HOLYOKE- BRIDGE BETTERMENT, H-21-024, LOWER WESTFIELD ROAD OVER PV RR
This is a proposed bride rehabilitation project consisting of a deck replacement on existing slightly modified stone masonry abutments. The approach roadway will include minor resurfacing and safety related improvements for approximately 475 feet on Lower Westfield Road. A traffic detour will be in effect during reconstruction.
|
Location: |
|
Resident Engineer: | Michael DeSimone |
Construction Contract Value: | $675,959.80 |
Construction Bid Price: | $614,196.00 |
Initial Construction Estimate: | $588,025.00 |
District: | District 2 |
Current Status: | Bridge under construction (as of 02/15/2008) |
Additional Info: | Bridge closed for duration of project. Traffic detoured from Lower Westfield Road to Whiting Farm Road to Route 5. (as of 03/31/2008) |
|