| Project Description: |
AGAWAM- SPRINGFIELD- BRIDGE REHABILITATION, A-05-001=S-24-005, ROUTE 5 OVER CONNECTICUT RIVER (JULIA B. BUXTON MEMORIAL BRIDGE)
AGAWAM- SPRINGFIELD- BRIDGE REHABILITATION, A-05-001=S-24-005, ROUTE 5 OVER CONNECTICUT RIVER (JULIA B. BUXTON MEMORIAL BRIDGE)
|
| Location: |
|
| Resident Engineer: | Edward King![]() |
| Construction Contract Value: | $10,141,211.78 |
| Construction Bid Price: | $8,447,784.50 |
| Initial Construction Estimate: | $6,983,000.00 |
| District: | District 2 |
| Current Status: | Bridge under construction (as of 03/21/2006) |
| Additional Info: | All lanes open to traffic. (as of 03/21/2006) |
|