Project Description:
EASTON- BRIDGE REPLACEMENTS, E-06-002 & E-06-030, CENTRAL STREET OVER QUESET BROOK
The work under this project consists of replacing the two Central Street Bridges over the Queset Brook. The new bridges will be two-span precast concrete culverts with a 29.5-foot wide asphalt wearing surface. A 5-foot handicap accessible cement concrete sidewalk will be constructed on the west side of the structures. The roadway approaches to the bridge will essentially remain in the same alignment with a proposed 5 foot sidewalk on the west side of Central Street. The limits of work on Central Street will extend to the Washington Street intersection. The bridges will be closed during construction to minimize the construction duration. The detour length is approximately 1.86 miles via Washington Street and Depot Street.
Location:
  • Town of Easton
  • Resident Engineer: John Bielski
    Construction Contract Value: $1,135,180.00
    Construction Bid Price: $1,089,280.00
    Initial Construction Estimate: $1,425,005.00
    District: District 5

    Contracts (2) Progress
    # 51409 -- Construction Contract
    Easton - 2 Bridges Superstructure Replacements (E-06-002 & E-06-030) (Concrete) Both on Central Street over Queset Brook Completed
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/23/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/25/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Review Committee Letter 09/20/1999
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 07/12/2006
    100% Design 100% Package Comments to DE 08/14/2006
    25% Design 25% Package Received 01/31/2003
    25% Design 25% Package Comments to DE 06/23/2003
    25% Design Design Public Hearing 11/17/2004
    75% Design 75% Package Received 03/21/2006
    75% Design 75% Package Comments to DE 05/26/2006
    Final Design PS&E Received 08/15/2006
    Final Design PS&E to FAPRO 08/17/2006
    Consultant Contract Process Scope to DE 09/18/2001
    Consultant Contract Process NTP Issued 04/05/2002
    Consultant Contract Process Workhours Approved 03/26/2002