Project Description:
FRAMINGHAM- BRIDGE REPLACEMENT, F-07-009, CENTRAL STREET OVER SUDBURY RIVER, INCLUDES REHAB OF WICKFORD ROAD BRIDGE, F-07-064
The proposed project consists of replacing the existing Central Street bridge over the Sudbury River in its present location with minor improvements to the approach roadways. The bridge will be closed during construction with a detour for traffic utilizing the Wickford Road bridge which will be rehabilitated as part of this project prior to the Central Street bridge.
Location:
  • Town of Framingham
  • Resident Engineer: Scott Kallin
    Construction Contract Value: $5,609,905.52
    Construction Bid Price: $4,414,563.00
    Initial Construction Estimate: $6,209,106.50
    District: District 3

    Contracts (5) Progress
    # 55858 -- Design -- Hwy Eng Open End
    Work will consist of providing services on an open end basis for various projects which require Chapter 253 Dam Safety Permit Review and Completion. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75497 -- Construction Contract
    2 Bridge Superstructure Replacements Br. No. F-07-009 Central Street (Concrete) and F-07-064 Wickford Road (Steel) both over the Sudbury River Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/22/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/02/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Status Advertised 09/08/2012
    Project Management
    100% Design 100% Package Received 12/09/2011
    100% Design 100% Package Comments to DE 02/27/2012
    25% Design 25% Package Received 01/28/2002
    25% Design 25% Package Comments to DE 04/13/2012
    25% Design 25% Package Approved 04/14/2004
    25% Design Design Public Hearing 04/14/2004
    25% Design Design Public Hearing 04/17/2012
    25% Design 25% Plans Complete 04/14/2004
    75% Design 75% Package Received 01/15/2008
    75% Design 75% Package Comments to DE 06/05/2008
    75% Design 75% Plans Approved 03/27/2009
    Final Design PS&E Received 08/28/2012
    Final Design PS&E to FAPRO 08/29/2012
    Consultant Contract Process NTP Issued 01/24/1999