GEORGETOWN- RECONSTRUCTION ON ROUTE 97 (W. MAIN STREET) FROM MOULTON STREET TO GROVELAND T.L.
The work on this project consists of roadway rehabilitation from Moulton Street to the Groveland/Georgetown town line. The proposed improvements include replacing a culvert, straightening and smoothing out the roadway, and replacing the drainage system.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Autumn 2026 |
| Project Manager: | Janhavi Limaye![]() |
| Estimated Total Contract Cost: | $10,758,734.48 |
| Estimated Total Federal Participating Construction Cost: | $11,198,915.73 |
| Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization. |
| District: | District 4 |
| Current Status: | 75% Package Received - Resub 1 (as of 06/03/2025 ) |
|