| Project Description: |
GEORGETOWN- RECONSTRUCTION ON ROUTE 97 (WEST MAIN STREET), FROM MOULTON STREET TO ROCK POND BOAT RAMP (PHASE 1)
The work on this project consists of roadway rehabilitation from Moulton Street to the Groveland/Georgetown town line. The proposed improvements include replacing a culvert, straightening and smoothing out the roadway, and replacing the drainage system.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Autumn 2027 |
| Project Manager: | Janhavi Limaye![]() |
| Estimated Total Contract Cost: | $14,044,324.28 |
| Estimated Total Federal Participating Construction Cost: | $13,813,409.40 |
| District: | District 4 |
| Current Status: | 100% Package Received (as of 07/01/2026 ) |
|
Bridges
|
||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||