GEORGETOWN- RECONSTRUCTION ON ROUTE 97 (W. MAIN STREET) FROM MOULTON STREET TO GROVELAND T.L.
The work on this project consists of roadway rehabilitation from Moulton Street to the Groveland/Georgetown town line. The proposed improvements include replacing a culvert, straightening and smoothing out the roadway, and replacing the drainage system.
Location:
  • Town of Georgetown
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $9,365,770.80
    Estimated Total Federal Participating Construction Cost: $10,749,455.95
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 03/14/2023 )

    Contracts (1) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: GEORGETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,030,382.40
    State Cost: $1,257,595.60
    Total Cost: $6,287,978.00

    Planned Federal FY: 2026
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: GEORGETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,913,164.80
    State Cost: $978,291.20
    Total Cost: $4,891,456.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/01/1998
    Project Review Committee PRC Tabled 01/11/1999
    Project Review Committee PRC Approved 05/24/1999
    Project Review Committee Letter 06/01/2000
    Project Management
    25% Design 25% Package Received 05/25/2000
    25% Design 25% Package Comments to DE 10/24/2007
    25% Design 25% Package Comments to DE 06/06/2008
    25% Design 25% Package Received - Resub 1 02/15/2017
    25% Design 25% Package Received - Resub 2 01/27/2020
    25% Design Design Public Hearing 02/07/2022
    75% Design 75% Package Received 12/08/2022
    75% Design 75% Package Comments to DE 03/14/2023
    Consultant Contract Process NTP Issued 09/15/2005