Project Description:
WEBSTER- INTERSECTION & SIGNAL IMPROVEMENTS ON ROUTE 12 (WEBSTER ROAD & E. MAIN ST) AT ROUTES 16 (GORE ROAD) & 193 (THOMPSON ROAD)
The proposed project includes horizontal alignment improvements of the north/south legs (Routes 12 and 193) of the intersection, the construction of exclusive left turn lanes on all four approaches, the construction of exclusive right turn lanes on two approaches, the construction of two westbound through lanes, and the installation of a new multiphase traffic signal. The proposed roadway width will consist of 11' travel lanes with 1.6' to 4' shoulders toaccommodate bicycles. Existing sidewalks disturbed by the proposed construction will be reestablished adjacent to the new edge of road.
Location:
  • Town of Webster
  • Resident Engineer: Paul Thompson
    Construction Contract Value: $2,021,370.00
    Construction Bid Price: $1,642,154.96
    Initial Construction Estimate: $1,808,814.00
    District: District 3

    Contracts (1) Progress
    # 59456 -- Construction Contract
    Intersection Reconstruction and Related Work at Route 12/16/193 (Worcester/Gore/Thompson Roads) and East Main Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/16/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    project on hold
    Construction starts March 29, 2010. Drainage and box widenings
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/14/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Review Committee Letter 12/01/1998
    Project Status Advertised 09/13/2008
    Project Status Advertised 05/02/2009
    Project Management
    100% Design 100% Package Received 08/27/2007
    100% Design 100% Package Received 06/30/2008
    100% Design 100% Package Comments to DE 01/31/2008
    100% Design 100% Package Comments to DE 08/08/2008
    25% Design 25% Package Received 11/17/2003
    25% Design 25% Package Comments to DE 03/18/2004
    25% Design Design Public Hearing 06/24/2004
    75% Design 75% Package Received 06/30/2006
    75% Design 75% Package Comments to DE 11/07/2006
    Final Design PS&E Received 09/03/2008
    Final Design PS&E Received 02/06/2009
    Final Design PS&E Received 02/06/2009
    Final Design PS&E to FAPRO 09/05/2008
    Final Design PS&E to FAPRO 03/06/2009