Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BELCHERTOWN- BRIDGE REPLACEMENT, BR# B-05-027, ROUTE 9 OVER SWIFT RIVER
This project will result in the demolition of the existing bridge and substructure. Along with the construction of a new bridge, the approach roadways will be reconstructed, retaining walls will be constructed and guardrail, pavement markings, temporary traffic signals, and other incidental work be provided.
Location:
  • Town of Belchertown
  • Resident Engineer: Jane Trudeau
    Construction Contract Value: $2,103,394.00
    Construction Bid Price: $1,867,631.50
    Initial Construction Estimate: $1,513,380.00
    District: District 2
    Current Status: Both lanes opened to traffic (as of 06/15/2007)

    Contracts (1) Progress
    # 42409 -- Construction Contract
    Belchertown - Ware - Bridge Replacement Route 9 over Swift River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/21/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Both lanes opened to traffic
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/19/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 03/05/2005
    Project Management
    100% Design 100% Package Received 06/24/2004
    100% Design 100% Package Comments to DE 09/09/2004
    25% Design 25% Package Received 09/01/2002
    25% Design 25% Package Comments to DE 07/16/2003
    25% Design Design Public Hearing 05/08/2003
    75% Design 75% Package Received 11/06/2003
    75% Design 75% Package Comments to DE 03/12/2004
    Final Design PS&E Received 01/04/2005
    Final Design PS&E to FAPRO 02/25/2005