Project Description:
WINCHENDON- BRIDGE REPLACEMENT, BR# W-39-018, ROUTE 202 (GLENALLEN STREET) OVER NORTH BRANCH OF MILLERS RIVER
The proposed project will replace the bridge in the same location as the existing structure. A new sidewalk will replace the existing sidewalk on the west side of the bridge. Minor improvements to the approach roadway are also included. The bridge will be replaced in two stages, allowing for traffic to cross during construction. A pedestrian walkway will be in place for the duration of the construction. Other improvements include pavement markings and new signage.
Location:
  • Town of Winchendon
  • Resident Engineer: Jane Trudeau
    Construction Contract Value: $1,537,330.00
    Construction Bid Price: $1,262,118.80
    Initial Construction Estimate: $951,812.00
    District: District 2
    Current Status: Bridge under construction (as of 02/06/2007)
    Additional Info: One lane alternating traffic with temporary traffic signals (as of 04/03/2007)

    Contracts (2) Progress
    # 32182 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract O Final
    # 45713 -- Construction Contract
    Wichendon - Route 202 (Glenallen St) over the N. Br. of Millers River Bridge No. W-39-018 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/20/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction
    Additional Info
    One lane alternating traffic with temporary traffic signals
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/20/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 09/24/2005
    Project Management
    100% Design 100% Package Received 07/14/2005
    100% Design 100% Package Comments to DE 08/09/2005
    25% Design 25% Package Received 09/13/2004
    25% Design 25% Package Comments to DE 09/22/2004
    25% Design Design Public Hearing 08/18/2004
    75% Design 75% Package Received 03/11/2005
    75% Design 75% Package Comments to DE 05/06/2005
    Final Design PS&E Received 08/26/2005
    Final Design PS&E to FAPRO 08/26/2005