Project Description:
SOUTHAMPTON- BRIDGE REPLACEMENT, BR# S-19-009 ROUTE 10 (COLLEGE HIGHWAY) OVER MANHAN RIVER
The work consists of repairing the substructure and replacing the existing bridge deck structure with a single span reinforced concrete bridge structure in approximately the same location. The work also includes reconstructing the approach roadways and adjacent traffic signal. Incidental items of work include clearing and grubbing, demolition, drainage adjustments, new pavement, curb, sidewalks with wheelchair ramps, temporary traffic signals, and traffic safety controls.
Location:
  • Town of Southampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Joseph Mombrun
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 08/02/2003 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/1998
    Project Status Advertised 09/14/2002
    Project Status Advertised 08/02/2003
    Project Management