Project Description:
ALFORD- GREAT BARRINGTON- BRIDGE REPLACEMENT, A-06-003, ALFORD ROAD OVER ALFORD BROOK
The purpose of this project is to replace the existing structurally deficient bridge structure carrying Alford Road over the Alford Brook in the Towns of Alford and Great Barrington. The existing bridge, which was built in 1937, has a curb-to-curb width of 26 feet and will be maintained by the proposed structure. The proposed bridge will be constructed of butted concrete deck beams supported on integral abutments. The demolition of the existing structure and construction of the new bridge will utilize staged construction.
Location:
  • Town of Alford
  • Town of Great Barrington
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $1,318,720.00
    Construction Bid Price: $1,145,148.50
    Initial Construction Estimate: $1,338,964.00
    District: District 1

    Contracts (4) Progress
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 58596 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 75351 -- Construction Contract
    Bridge Replacement (A-06-003) (Precast Concrete) - Alford Road over Alford River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/11/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/09/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 09/01/2012
    Project Management
    25% Design 25% Package Received 04/14/2011
    25% Design 25% Package Comments to DE 06/01/2011
    25% Design 25% Package Approved 10/17/2011
    25% Design Design Public Hearing 11/17/2011
    25% Design 25% Plans Complete 10/13/2011
    75% Design 75% Package Received 03/16/2012
    75% Design 75% Package Comments to DE 04/30/2012
    75% Design 75% Plans Approved 04/30/2012
    75% Design 75% Plans Complete 03/19/2012
    Final Design PS&E Received 08/01/2012
    Final Design PS&E to FAPRO 08/28/2012
    Consultant Contract Process Scope to DE 06/16/2010
    Consultant Contract Process Scope to DE 08/20/2010
    Consultant Contract Process Scope to DE 09/03/2010
    Consultant Contract Process Scope to DE 09/10/2010
    Consultant Contract Process Scope to DE 09/21/2010
    Consultant Contract Process NTP Issued 10/22/2010
    Consultant Contract Process Workhours Approved 10/13/2010