MATTAPOISETT- MULTI-USE PATH CONSTRUCTION (PENN CENTRAL RIGHT OF WAY) FROM FAIRHAVEN T.L. TO MATTAPOISETT NECK ROAD (PHASE 1A)
The work under the Phase 1A section of the Mattapoisett Bike Path project consists of constructing a two-way 10 foot wide multi-use path beginning at the Fairhaven/ Mattapoisett town line and extending approximately 3,900 feet east to Mattapoisett Neck Road. The work includes construction of a bituminous concrete multi-use surface with gravel foundation on the existing railroad bed, drainage improvements and utility relocations as necessary, application of pavement markings and signs, and incidental landscaping as necessary. Subsequent design phases will need follow to complete the Mattapoisett Bike Path.
Location:
  • Town of Mattapoisett
  • Resident Engineer: Charles Hodges Jr
    Construction Contract Value: $501,555.00
    Construction Bid Price: $421,414.25
    Initial Construction Estimate: $510,295.00
    District: District 5

    Contracts (1) Progress
    # 53934 -- Construction Contract
    Matapoisett - Construction of a Multi-Use Path (Phase 1A) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/20/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/11/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Review Committee Letter 11/01/1998
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 06/14/2007
    100% Design 100% Package Comments to DE 07/31/2007
    25% Design 25% Package Received 06/08/2006
    25% Design 25% Package Comments to DE 05/21/2001
    25% Design Design Public Hearing 08/29/2001
    75% Design 75% Package Received 07/05/2006
    75% Design 75% Package Comments to DE 09/25/2006
    Final Design PS&E Received 08/17/2007
    Final Design PS&E to FAPRO 08/28/2007