NEW MARLBOROUGH- BRIDGE REPLACEMENT, N-08-013, MILL RIVER ROAD OVER THE KONKAPOT RIVER
This project involves rehabilitating the Mill River Road Bridge with a new bridge deck on the existing bridge abutments, which are to be repaired. The new bridge will be widened by approximately 3.3 feet. The bridge is proposed to remain open during staged construction.
Location:
  • Town of New Marlborough
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $1,330,038.79
    Construction Bid Price: $1,220,212.10
    Initial Construction Estimate: $1,122,013.12
    District: District 1

    Contracts (3) Progress
    # 32173 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract F Final
    # 32178 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract K Final
    # 39967 -- Construction Contract
    New Marlborough - Bridge Replacement (N-18-13) (Steel) Mill River Road over Konkapot River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/27/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/07/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 01/10/2006
    100% Design 100% Package Comments to DE 02/24/2006
    100% Design 100% Plans Approved 05/05/2006
    100% Design 100% Plans Complete 05/05/2006
    25% Design 25% Package Comments to DE 11/02/2000
    25% Design Design Public Hearing 02/13/2001
    75% Design 75% Package Received 05/12/2005
    75% Design 75% Package Comments to DE 07/01/2005
    Final Design PS&E Received 05/05/2006
    Final Design PS&E to FAPRO 06/07/2006