Project Description:
NORTHAMPTON- NORWOTTUCK RAIL-TRAIL EXTENSION, FROM LOOK PARK TO LEEDS, INCLUDES N-19-073 (LOOK PARK) & N-19-044 (ARCH STREET)
This project consists of constructing a 2.0 mile long paved trail along a section of an abandoned rail corridor. The project begins at the terminus of the existing Northampton Bike Path near Bridge Street/Look Park and proceeds northwest to the end of Grove Avenue near the Williamsburg town line. Proposed work items include: construction of a 10-foot wide paved path, safety railings, bridge replacement, culvert repair/replacement, traffic signs, pavement markings, clearing and grubbing, and erosion control measures.
Location:
  • City of Northampton
  • Resident Engineer: Joseph Burek
    Construction Contract Value: $2,131,134.76
    Construction Bid Price: $1,757,998.10
    Initial Construction Estimate: $1,909,118.60
    District: District 2

    Contracts (1) Progress
    # 57072 -- Construction Contract
    Northampton - Construction of the Norwottuck Bike Path Extension Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/22/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/22/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 07/26/2008
    Project Management
    100% Design 100% Package Received 05/01/2008
    100% Design 100% Package Comments to DE 05/16/2008
    25% Design Design Public Hearing 12/07/1999
    75% Design 75% Package Received 06/04/1999
    75% Design 75% Package Comments to DE 06/06/2001
    75% Design 75% Plans Approved 12/19/2001
    Final Design PS&E Received 05/01/2008