NORTHAMPTON- BIKE PATH CONSTRUCTION ON STATE STREET (DOWNTOWN LINK NORWOTTUCK RAIL TRAIL) INCLUDES N-19-005 & N-19-006
The project is for the construction of approximately 8,000 feet of bike trail. The trail follows the path of the former railroad tracks, starting at the existing bike trail near State Street and Stoddard Street and ending at New South Street. It also includes 3 new pedestrian/bike bridges over King, North, and Main Streets, the reconstruction of culverts and catch basins at the Pleasant Street crossing, and the reconstruction of parking lots near the King and Main Street crossings.
Location:
  • City of Northampton
  • Resident Engineer: Daniel Boucher
    Construction Contract Value: $3,023,333.00
    Construction Bid Price: $2,103,723.37
    Initial Construction Estimate: $2,094,689.65
    District: District 2

    Contracts (1) Progress
    # 53961 -- Construction Contract
    Northampton - Construction of Downtown Link of Manhan Rail Trail Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/24/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/22/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 08/18/2007
    Project Management
    100% Design 100% Package Received 08/06/2002
    100% Design 100% Package Comments to DE 12/12/2002
    25% Design Design Public Hearing 03/22/2001
    75% Design 75% Package Received 08/25/2000
    Final Design PS&E Received 07/31/2007
    Final Design PS&E to FAPRO 08/14/2007