Project Description:
FAIRHAVEN- RESURFACING & SIGNAL IMPROVEMENTS ON A SECTION OF ROUTE 240, FROM I-195 TO ROUTE 6
The purpose of this project is to resurface Route 240, from Route I-195 to the Rte 6. The project includes upgrades to traffic signals and installation of pavement markings.
Location:
  • Town of Fairhaven
  • Resident Engineer: Alfredo Nunez
    Construction Contract Value: $1,798,390.00
    Construction Bid Price: $1,526,000.00
    Initial Construction Estimate: $1,547,642.00
    District: District 5

    Contracts (2) Progress
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 60369 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 240. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/22/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/31/1998
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 09/05/2009
    Project Management
    100% Design 100% Package Received 08/21/2009
    25% Design 25% Package Received 06/24/2009
    25% Design 25% Package Comments to DE 07/23/2009
    25% Design 25% Package Approved 07/24/2009
    25% Design Design Public Hearing 07/06/2009
    Final Design PS&E Received 08/28/2009
    Final Design PS&E to FAPRO 09/02/2009