Project Description: |
FAIRHAVEN- RESURFACING & SIGNAL IMPROVEMENTS ON A SECTION OF ROUTE 240, FROM I-195 TO ROUTE 6
The purpose of this project is to resurface Route 240, from Route I-195 to the Rte 6. The project includes upgrades to traffic signals and installation of pavement markings.
|
Location: |
|
Resident Engineer: | Alfredo Nunez |
Construction Contract Value: | $1,798,390.00 |
Construction Bid Price: | $1,526,000.00 |
Initial Construction Estimate: | $1,547,642.00 |
District: | District 5 |
|
Bridges |
|
|
|
|