Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STERLING- TRAFFIC SAFETY IMPROVEMENTS INCLUDING SIGNALS, REDEMPTION ROCK TRAIL (ROUTE 140) AT DANA HILL ROAD AND LEGG ROAD
Location:
  • Town of Sterling
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Philip Macdonald
    Estimated Total Federal Participating Construction Cost: $350,000.00
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 09/15/2001 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/04/1999
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 09/15/2001
    Project Management