Project Description:
GROTON- TRAFFIC SIGNALS, ROUTE 119 (BOSTON ROAD), ROUTE 225 (FORGE VILLAGE RD), SANDY POND ROAD
The purpose of this project is to install a new traffic signal at the four-way intersection of Route 119 (Boston Road), Forge Village Road (Route 225) and Sandy Pond Road in the Town of Groton. The roadway will be reconstructed from the intersection for approximately 560 meters along Route 119 (Boston Road), 180 meters along Forge Village Road (Route 225), 160 meters along Sandy Pond Road and 120 meters along Whiley Road. The work also includes upgrades to the existing drainage system, installation of granite vertical curb and sloped edging, constructing a cement concrete sidewalk with wheelchair ramps, loam and seed, landscaping, signing, pavement markings, safety controls and signing for construction and all other items required to complete the work. The work also includes the demolition and removal of the former Groton Jade Restaurant located on the southeast corner of Sandy Pond Road.
Location:
  • Town of Groton
  • Resident Engineer: Steven Toloczko
    Construction Contract Value: $1,531,246.00
    Construction Bid Price: $1,595,842.00
    Initial Construction Estimate: $1,650,284.75
    District: District 3
    Current Status: Adjustment to signs remains to complete punch list. (as of 06/30/2006)

    Contracts (2) Progress
    # 3431 -- Design -- Bike/Ped Projects
    INTERSECTION RECONSTRUCTION - ROUTE 119 (BOSTON RD) AT ROUTE 225 - STP-001S(292)X Final
    # 35034 -- Construction Contract
    Intersection Reconstruction on Route 119 (Boston Road) at Route 225. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/20/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Adjustment to signs remains to complete punch list.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/05/1999
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 05/22/2004
    Project Management
    100% Design 100% Package Received 06/25/2003
    100% Design 100% Package Comments to DE 10/03/2003
    100% Design 100% Plans Complete 04/15/2004
    75% Design 75% Package Received 06/25/2003
    Final Design PS&E Received 04/20/2004
    Final Design PS&E to FAPRO 05/17/2004