Project Description:
CHICOPEE- CONNECTICUT RIVERWALK & BIKEWAY CONSTRUCTION, FROM BOAT RAMP NEAR I-90 TO NASH FIELD (2.5 MILES), INCLUDES NEW BRIDGE C-13-060 OVER OVERFLOW CHANNEL
The proposed project consists of constructing a Riverwalk and Bikeway along the Connecticut River in the City of Chicopee, beginning at the boat ramp near I-90 and extending northward to Nash Field, for a total length of approximately 2.5 miles.
Location:
  • City of Chicopee
  • Construction Begins: Summer 2020
    Resident Engineer: Christopher Hoynoski
    Construction Bid Price: $2,597,614.00
    District: District 2

    Contracts (1) Progress
    # 111025 -- Construction Contract
    Connecticut Riverwalk and Bikeway Construction (Including Prefabricated Pedestrian Bridge) Medina Street to Ferry Street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/16/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/11/1999
    Project Review Committee PRC Approved 10/20/1999
    Project Status Advertised 03/14/2020
    Project Management
    100% Design 100% Package Received 09/18/2017
    100% Design 100% Package Comments to DE 06/13/2018
    25% Design 25% Package Received 09/17/2013
    25% Design 25% Package Comments to DE 01/24/2014
    25% Design Design Public Hearing 08/06/2014
    75% Design 75% Package Received 06/13/2016
    Final Design PS&E Received 03/26/2019
    Final Design Peer Review Comments to DE 05/24/2019
    Final Design PS&E Received - Resub 3 02/13/2020
    Consultant Contract Process NTP Issued 08/13/1998