YARMOUTH- PEDESTRIAN & SITE IMPROVEMENTS ON ROUTE 28 @ BASS RIVER TOWN PROPERTY ABUTTING BASS RIVER (PACKETT'S LANDING)
This project is a High Priority Project earmark in TEA-21. The project consists of land acquisition and design and construction of a parking facility adjacent to BassRiver and the Packett's Landing Boat Ramp. Included in the project is site preparation, building demolition, landscaping and paving to construct the facility. On the proposed site the town will restore a historic building, the work for which is not included in the project.
Location:
  • Town of Yarmouth
  • Resident Engineer: Joseph Gedraitis
    Construction Contract Value: $882,140.50
    Construction Bid Price: $749,692.88
    Initial Construction Estimate: $742,670.00
    District: District 5

    Contracts (1) Progress
    # 56793 -- Construction Contract
    Yarmouth- Site Improvements at Packett's Landing (on Route 28 at the Bass River) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/01/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/10/1999
    Project Review Committee PRC Tabled 05/24/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Review Committee Letter 10/20/1999
    Project Status Initiated 08/24/1999
    Project Status Advertised 07/12/2008
    Project Management
    100% Design 100% Package Received 12/10/2007
    100% Design 100% Package Comments to DE 02/06/2008
    25% Design 25% Package Received 04/21/2006
    25% Design 25% Package Comments to DE 07/10/2006
    25% Design Design Public Hearing 09/14/2006
    75% Design 75% Package Received 01/05/2007
    75% Design 75% Package Received 02/23/2007
    75% Design 75% Package Comments to DE 03/15/2007
    Final Design PS&E Received 03/28/2008
    Final Design PS&E to FAPRO 04/16/2008