Project Description:
HOLYOKE- REHABILITATION OF PLEASANT STREET, FROM 580 FEET SOUTH OF YALE STREET NORTHERLY TO NORTHAMPTON STREET
This project shall consist of roadway and sidewalk rehabilitation along Pleasant Street from 580 feet south of Yale Street to Northampton Street, a project length of 4,743 feet.
Location:
  • City of Holyoke
  • Resident Engineer: Daniel Kaminski
    Construction Contract Value: $1,478,869.48
    Construction Bid Price: $1,307,628.55
    Initial Construction Estimate: $1,532,453.00
    District: District 2

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 69459 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Pleasant Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/29/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/15/1999
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 12/16/2002
    Project Status Advertised 06/25/2011
    Project Management
    100% Design 100% Package Received 02/24/2011
    100% Design 100% Package Comments to DE 05/10/2011
    25% Design 25% Package Received 08/03/2007
    25% Design 25% Package Comments to DE 09/24/2008
    25% Design Design Public Hearing 03/31/2009
    75% Design 75% Package Received 12/17/2009
    75% Design 75% Package Comments to DE 01/13/2011
    Final Design PS&E Received 06/21/2011
    Final Design PS&E to FAPRO 06/22/2011