BROOKLINE- FRAMINGHAM- NATICK- NEWTON- SOUTHBOROUGH- WELLESLEY- WESTBOROUGH- TRAFFIC SIGNS ON ROUTE 9
This project will replace and update all overhead and ground-mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on Route 9 and secondary roadways from the Boston-Brookline town line to I-495 in Westborough, with the exception of signing which was updated under the I-495 Milford to Bolton contract.
Location:
  • Town of Brookline
  • Town of Framingham
  • Town of Natick
  • City of Newton
  • Town of Southborough
  • Town of Wellesley
  • Town of Westborough
  • Resident Engineer: Alan Webb
    Construction Contract Value: $2,502,082.00
    Construction Bid Price: $2,113,340.40
    Initial Construction Estimate: $2,694,809.50
    District: District 3
    Additional Info: 602930 (as of 02/08/2008)

    Contracts (1) Progress
    # 43803 -- Construction Contract
    Replacement of guide and traffic signs on State Route 9 between Washington Street in Brookline and I-495 in Westborough Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/15/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Additional Info
    602930
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/24/1999
    Project Review Committee PRC Approved 05/24/1999
    Project Status Advertised 08/06/2005
    Project Management
    Final Design PS&E Received 07/25/2005