Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LOWELL- BRIDGE REPLACEMENT, L-15-058, VFW HIGHWAY OVER BEAVER BROOK
The purpose of this project is to replace the existing bridge and bridge approaches.
Location:
  • City of Lowell
  • Construction Begins: Spring 2016
    Resident Engineer: Ann Roche
    Construction Bid Price: $12,197,044.31
    District: District 4

    Contracts (6) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90724 -- Construction Contract
    Bridge Replacement Br. No. L-15-058 (Steel) VFW Highway over Beaver Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/13/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/14/1998
    Project Review Committee PRC Approved 06/04/2012
    Project Status Initiated 11/22/2006
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 08/31/2015
    25% Design 25% Package Received 11/10/2014
    25% Design 25% Package Received 03/20/2015
    25% Design 25% Package Comments to DE 01/22/2015
    75% Design 75% Package Received 06/16/2015
    Final Design PS&E Received 09/11/2015
    Final Design PS&E Received 12/18/2015
    Final Design PS&E Received 01/13/2016
    Final Design PS&E to FAPRO 09/14/2015
    Consultant Contract Process NTP Issued 03/14/2005