Project Description:
ERVING- RELOCATION OF A SECTION OF ROUTE 2 AT THE ERVING PAPER MILL
This project consists of the relocation of a 1-mile section of Route 2, approximately 340 feet north of the existing Route 2. The project is located east of the Erving Town Hall near the Erving Paper Mill. The proposed project will improve substandard roadway geometry and inadequate sight distances. The sidewalk will be improved to provide continuity between the Town center and the Paper Mill. The project will eliminate the need for Paper Mill employees to cross Route 2 from the Paper Mill parking lot, and will also reduce the through traffic interference caused by trucks using the Paper Mill loading docks. A left turn lane will be provided on the new Route 2 westbound at the new Paper Mill driveway.
Location:
  • Town of Erving
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $8,448,780.77
    Construction Bid Price: $7,156,434.00
    Initial Construction Estimate: $8,318,055.00
    District: District 2
    Current Status: Roadway under construction (as of 05/15/2006)
    Additional Info: Work suspended until Spring. When work resumes, daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 01/04/2008)

    Contracts (2) Progress
    # 34465 -- Construction Contract
    Reconstruction of a Section of Route 2. Completed
    # 99102 -- Design -- Highway
    Erving - Relocation of Route 2 art Erving Paper Mill Prelim & Final Design Services Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/09/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Roadway under construction
    Additional Info
    Work suspended until Spring. When work resumes, daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 08/09/2003
    Project Management