Project Description:
ORANGE- IMPROVEMENTS ALONG ROUTE 2, INCLUDES REHAB OF O-03-022 & CONSTRUCTION OF 0-03-026 (WILD LIFE PASSAGE)
This project consists of safety improvements and upgrades along Route 2 in the Town of Orange for a length of approximately 5 miles. This project includes widening the shoulder, extending the existing climbing lanes, and improving the acceleration and deceleration lanes and the alignments at various on/off ramps. In addition, the Route 2 bridge over Route 122 will be widened and the superstructure replaced to accommodate the proposed widened climbing lane.
Location:
  • Town of Orange
  • Resident Engineer: Ralph Romano
    Construction Contract Value: $14,558,547.00
    Construction Bid Price: $11,757,225.15
    Initial Construction Estimate: $16,203,983.00
    District: District 2

    Contracts (6) Progress
    # 32147 -- Design -- Hwy Eng Open End
    Statewide - Provide engineering design and review services to the Highway Engineering Division on an open end basis for highway and bridge projects. Final
    # 41073 -- Design -- Bridge Rehab/Recon/New Const
    Review the preliminary design done by others and completion of the final design for the safety improvements project in the Town of Orange. Final
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62669 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 2 (Mohawk Trail). (ARRA Project) Completed
    # 99106 -- Design -- Highway
    Orange - Route 2 Safety Improvements Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/18/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 01/23/2010
    Project Management
    100% Design 100% Package Received 07/26/2006
    100% Design 100% Package Received 08/11/2008
    100% Design 100% Package Comments to DE 11/30/2006
    100% Design 100% Package Comments to DE 11/06/2008
    25% Design 25% Package Received 03/16/2001
    25% Design 25% Package Comments to DE 05/17/2001
    25% Design 25% Package Approved 10/27/2004
    25% Design Design Public Hearing 09/19/2001
    75% Design 75% Package Received 12/23/2005
    75% Design 75% Package Comments to DE 04/12/2006
    Final Design PS&E Received 03/20/2009
    Final Design PS&E Received 06/23/2009
    Final Design PS&E Received 12/24/2009
    Final Design PS&E to FAPRO 12/30/2009
    Consultant Contract Process Scope to DE 02/24/2005
    Consultant Contract Process NTP Issued 08/02/2005
    Consultant Contract Process Workhours Approved 04/01/2005