ATHOL- PHILLIPSTON- SAFETY IMPROVEMENTS ALONG ROUTE 2 INCLUDING INSTALLATION OF MEDIAN BARRIER
This project consists of the reconstruction of a 6.95 mile portion of Route 2 in the Towns of Athol and Phillipston and will address existing safety and operational deficiencies within this corridor. The project also includes a new climbing lane, improvements to acceleration and deceleration lanes, a new truck weigh station, installation of a median barrier, police pullouts, and significant drainage system improvements.
Location:
  • Town of Athol
  • Town of Phillipston
  • Resident Engineer: William Whiteman
    Construction Contract Value: $17,926,770.91
    Construction Bid Price: $13,858,069.00
    Initial Construction Estimate: $14,356,960.00
    District: District 2
    Current Status: Physical work complete (as of 10/17/2007)

    Contracts (2) Progress
    # 38599 -- Construction Contract
    Athol - Phillipston - Safety Improvements on a Section of Route 2 Completed
    # 99105 -- Design -- Highway
    Athol - Phillipston Route 2 Safety Improvements Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/04/2004
    Project Management
    100% Design 100% Package Received 06/29/2004
    100% Design 100% Package Comments to DE 07/20/2004
    25% Design 25% Package Received 10/02/2000
    25% Design 25% Package Comments to DE 11/09/2000
    25% Design Design Public Hearing 10/10/2001
    75% Design 75% Package Received 01/26/2004
    75% Design 75% Package Comments to DE 03/12/2004
    Final Design PS&E Received 07/23/2004
    Final Design PS&E to FAPRO 07/23/2004