Project Description:
FRAMINGHAM- BRIDGE REHABILITATION, BR# F-07-005, MAIN STREET OVER SUDBURY RIVER
The proposed Main Street Bridge Rehabilitation Project includes repair of the existing bridge abutments along with replacement of deteriorated steel truss members. Minor approach work will include guardrail, pavement markings and minor repair to the historical bridge rail and elliptical trusses. The bridge will continue to be closed during the construction period and a detour will be in place.
Location:
  • Town of Framingham
  • Resident Engineer: Scott Kallin
    Construction Contract Value: $1,773,355.30
    Construction Bid Price: $1,416,657.00
    Initial Construction Estimate: $1,305,831.50
    District: District 3

    Contracts (1) Progress
    # 48023 -- Construction Contract
    Framingham - Bridge Rehabilitation (F-07-005) (Steel) - Main Street over the Sudbury River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/16/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/14/1999
    Project Review Committee PRC Approved 05/24/1999
    Project Review Committee Letter 09/15/2005
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 03/23/2005
    100% Design 100% Package Comments to DE 07/01/2005
    25% Design 25% Package Received 04/06/2001
    25% Design 25% Package Comments to DE 08/03/2001
    75% Design 75% Package Received 06/07/2002
    75% Design 75% Package Comments to DE 01/03/2003
    Final Design PS&E Received 09/08/2005
    Final Design PS&E to FAPRO 09/08/2005