GARDNER- WINCHENDON- CONSTRUCTION OF A BICYCLE PATH, NORTH CENTRAL PATHWAY (PHASE III)
The scope of work consists of the construction of approximately 3.5 miles of new trail within the railroad right-of-way, from the northerly side of Route 140 in Gardner to the intersection of the Railroad Right of Way with Old Gardner Road in Winchendon. The work includes bituminous concrete pavement, traffic control signing, crosswalks and other incidental work.
Location:
  • City of Gardner
  • Town of Winchendon
  • Resident Engineer: Steven Toloczko
    Construction Contract Value: $790,440.89
    Construction Bid Price: $717,473.54
    Initial Construction Estimate: $630,000.00
    District: District 3

    Contracts (1) Progress
    # 32138 -- Construction Contract
    Construction of Bicycle Path - North Central Pathway. (Phase III) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/05/2002
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/20/1999
    Project Review Committee PRC Approved 05/24/1999
    Project Status Advertised 09/15/2001
    Project Management