SOUTHBRIDGE- RECONSTRUCTION OF ROUTE 169 (WOODSTOCK ROAD) FROM THE CONNECTICUT S.L. TO ROUTE 131 (E. MAIN STREET)
This Footprint Road project involves milling and resurfacing, selected full-depth construction and minor box widening to provide a uniform width. (3.25 mi)
Location:
  • Town of Southbridge
  • Resident Engineer: Paul Thompson
    Construction Contract Value: $4,601,606.00
    Construction Bid Price: $4,084,860.00
    Initial Construction Estimate: $5,085,283.00
    District: District 3

    Contracts (1) Progress
    # 61269 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 169 (North Woodstock Road). (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/10/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 10/31/2002
    Project Review Committee Letter 06/09/2005
    Project Status Initiated 05/30/2006
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 09/08/2009
    25% Design 25% Package Received 06/12/2006
    25% Design 25% Package Comments to DE 11/01/2006
    25% Design Design Public Hearing 10/22/2008
    75% Design 75% Package Received 06/24/2009
    75% Design 75% Package Comments to DE 08/17/2009
    Final Design PS&E Received 09/15/2009
    Final Design PS&E to FAPRO 09/15/2009