FRANKLIN- RECONSTRUCTION ON KING STREET AND I-495 RAMPS
This is a safety and traffic improvements project. It extends along King Street from Union Street to Upper Union Street and also includes Upper Union Street from King Street to Constitution Boulevard and all four I-495 ramps at King Street. It involves roadway improvements as well as intersection signalization improvements. Project includes widening of King Street to provide two lanes in each direction with left and right turning lanes at appropriate locations; widening and realignment of Upper Union Street to make Constitution Boulevard the major traffic movement; upgrading the signals at the King and Upper Union Street intersection and providing two left turn lanes from King Street onto Upper Union Street. New signals will be installed at the intersections of I-495 southbound and northbound ramps, and the signals at the King and Union Street intersection will be upgraded. The signals along King Street will be synchronized to provide better traffic flow along King Street. Existing concrete pavement will be removed from all four I-495 ramps and ramps will be reconstructed with full depth asphalt pavement. In addition, project involves drainage improvements, curbing, new sidewalks, wheelchair ramps, pavement markings, signing, landscaping, a closed circuit television camera for traffic monitoring on I-495, and other incidental work. This project will require temporary and permanent easements for its implementation.
Location:
  • Town of Franklin
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $3,420,413.00
    Construction Bid Price: $3,328,101.85
    Initial Construction Estimate: $4,453,800.00
    District: District 3

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58839 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of King & Upper Union Streets and 4 Interstate I-495 Ramps. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/13/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/13/2000
    Project Review Committee PRC Tabled 05/24/1999
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 10/02/1999
    Project Status Advertised 12/27/2008
    Project Management
    100% Design 100% Package Received 07/28/2005
    100% Design 100% Package Comments to DE 09/23/2005
    100% Design 100% Package Comments to DE 03/06/2008
    25% Design 25% Package Received 10/22/2001
    25% Design 25% Package Comments to DE 02/28/2002
    25% Design Design Public Hearing 10/27/2003
    25% Design 25% Plans Complete 03/06/2003
    75% Design 75% Package Received 06/04/2004
    75% Design 75% Package Comments to DE 04/26/2005
    75% Design 75% Plans Complete 04/26/2005
    Final Design PS&E Received 10/06/2006
    Final Design PS&E Received 03/01/2007
    Final Design PS&E Received 09/10/2007
    Final Design PS&E Received 08/01/2008
    Final Design PS&E Received 12/17/2008
    Final Design PS&E to FAPRO 12/22/2008
    Consultant Contract Process Scope to DE 08/24/2009