| Project Description: |
DISTRICT 4- HIGHWAY MAINTENANCE DRAINAGE BETTERMENTS DISTRICT-WIDE VARIOUS LOCATIONS
This project consists of trenching and repair of existing drain lines; construction of new storm drains; placement of stones and geotextile fiber embankment stabilization at points of pipe or culvert discharge.
|
| Location: | |
| Resident Engineer: | Catherine Archis![]() |
| Construction Contract Value: | $1,622,886.02 |
| Construction Bid Price: | $893,849.25 |
| Initial Construction Estimate: | $609,400.00 |
| District: | District 4 |
| Current Status: | The contractor has completed drainage work in Weymouth on Rte 53 @ Canolli's Rester. Tewksbury on Rte 38 @ former police station and in Methuen at Rte 213 E.B. & Howe St. (as of 09/04/2007) |
| Additional Info: | This contract is complete as of 8/31/2007. (as of 09/04/2007) |
|