Project Description:
CONCORD- LINCOLN- LIMITED ACCESS HIGHWAY IMPROVEMENTS AT ROUTE 2 & 2A, BETWEEN CROSBY'S CORNER & BEDFORD ROAD, INCLUDES C-19-024
The purpose of this project is to provide safety improvements at Crosby’s Corner (intersection of Route 2, Cambridge Turnpike and Route 2A/ the Concord Turnpike). This will be accomplished by constructing neighborhood service roads which will be parallel to Route 2. This will also be accomplished by constructing a bridge to carry Route 2 over the other routes. The benefits of the project include the ability to safely and efficiently accommodate traffic and to provide safe access to the residences and businesses located along the project corridor. The project starts at the Bedford Road intersection in the Town of Lincoln and extends to 300 feet west of Sandy Pond Road in the Town of Concord.
Location:
  • Town of Concord
  • Town of Lincoln
  • Resident Engineer: Brian Polley
    Construction Contract Value: $48,160,546.00
    Construction Bid Price: $42,228,757.00
    Initial Construction Estimate: $51,828,136.00
    Total Estimated Project Cost: $65,000,000.00
    District: District 4

    Contracts (14) Progress
    # 32147 -- Design -- Hwy Eng Open End
    Statewide - Provide engineering design and review services to the Highway Engineering Division on an open end basis for highway and bridge projects. Final
    # 34533 -- Design -- Bridge Rehab/Recon/New Const
    Concord/Lincoln - Final Design Services to complete the project from the 25% Design Stage to the PSE/Advertising stage, including construction phase services for the diamond i Final
    # 41489 -- Design -- Geotechnical
    Statewide - implement geophysical methods on statewide designed and constructed bridge and highway projects. Final
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 56771 -- Design -- MEPA/NEPA Compliance
    Work will be assigned on an as-needed basis including Early Environmental Coordination and Public Outreach including Federal and State Agency coordination. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62936 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering on various projects.
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64322 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 71104 -- Construction Contract
    Roadway Reconstruction and Related Work (Including 1 Bridge and 14 Retaining Walls) along a Section of Route 2 (Crosbys Corner Interchange). Completed
    # 76262 -- Non-system contract type
    Perform various assignments as the Owner's Representative for the peer review of engineering elements associated with satewide construction projects.
    # 80660 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 06/11/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/19/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 07/15/2011
    100% Design 100% Package Comments to DE 08/15/2011
    25% Design 25% Package Received 05/15/2002
    25% Design 25% Package Comments to DE 03/23/2005
    25% Design 25% Package Approved 05/20/2004
    25% Design Design Public Hearing 05/13/2003
    75% Design 75% Package Received 01/21/2011
    75% Design 75% Package Comments to DE 03/31/2011
    75% Design 75% Package Rejected 11/07/2008
    Final Design PS&E Received 09/09/2011
    Final Design PS&E to FAPRO 09/12/2011
    Consultant Contract Process Scope to DE 10/04/2004
    Consultant Contract Process NTP Issued 03/15/2005