Project Description: |
CHESTER- BRIDGE REPLACEMENT, BR# C-11-004, HAMPDEN STREET OVER WALKER BROOK
The existing bridge is located near the intersection of Route 20 and Hampden Street. The proposed replacement bridge will consist of a single span high strength concrete bridge. The two lane bridge will be 25 feet wide with no sidewalk. The approach roadways will be widened to match the bridge width.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | Municipality |
Project Manager: | Luciano Rabito |
Estimated Total Contract Cost: | $895,236.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 1 |
Current Status: | This project is in the preliminary design phase. |
|