Project Description:
EAST BROOKFIELD- BRIDGE REPLACEMENT, E-02-002, SHORE ROAD OVER EAST BROOKFIELD RIVER
The purpose of this project is to replace the Shore Road bridge over the Brookfield River. Work on Shore Road will include roadway reconstruction and resurfacing approximately 260 feet west and approximately 300 feet east of the bridge. Traffic will be detoured approximately 6.2 miles during construction. Existing right-of-way will be adequate for this project. Temporary easements may be required. The Town of East Brookfield is responsible for acquiring all needed rights in private or public lands.
Location:
  • Town of East Brookfield
  • Resident Engineer: William Walker
    Construction Contract Value: $1,252,559.00
    Construction Bid Price: $1,074,856.00
    Initial Construction Estimate: $1,241,660.00
    District: District 3

    Contracts (3) Progress
    # 55040 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 71223 -- Construction Contract
    Bridge Replacement (E-02-002) (Concrete) - Shore Road over the East Brookfield River at Quaboag Pond. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/16/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/30/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/24/2011
    Project Management
    100% Design 100% Package Received 10/13/2010
    100% Design 100% Plans Complete 10/13/2010
    25% Design 25% Package Received 02/16/2001
    25% Design 25% Package Comments to DE 07/03/2008
    25% Design Design Public Hearing 12/13/2004
    75% Design 75% Package Received 07/23/2008
    75% Design 75% Package Comments to DE 11/13/2008
    Final Design PS&E Received 09/02/2011
    Final Design PS&E to FAPRO 09/20/2011