Project Description:
FALL RIVER- INSTALLATION OF A PRE-ACTION SPRINKLER SYSTEM AND A CARBON MONOXIDE MONITORING SYSTEM AT GOVERNMENT CENTER PLAZA
The work consists of furnishing all required equipment, labor and materials for the installation of a pre-action sprinkler system at the basement of the Fall River City Hall, and a carbon monoxide monitoring system at the Fall River City Hall Building.
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael Papadopoulos
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 02/03/2001 )

    Contracts (1) Progress
    # 99220 -- Design -- Highway
    Fall River City Hall Plaza Field Condition Assessment and Mechanical Analysis. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/15/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 02/03/2001
    Project Management
    Final Design PS&E Received 01/22/2001
    Final Design PS&E to FAPRO 01/22/2001